CASES REQUIRING TRIAL OPERATION OF WASTE TREATMENT FACILITIES

NO 01 SAI GON JSC.

Khu dân cư An Bình, 60 Lê Thị Vân, An Bình, Biên Hòa, Đồng Nai

Vietnam English Nhật Trung
CASES REQUIRING TRIAL OPERATION OF WASTE TREATMENT FACILITIES
21/03/2026 11:25 AM 239 Views

    Regulations on Trial Operation of Waste Treatment Facilities after the Issuance of an Environmental Permit (EP)

    (Pursuant to Article 31 of Decree No. 08/2022, as amended and supplemented by Decree No. 05/2025 and Decree No. 48/2026)


    1. Waste treatment facilities NOT subject to trial operation include:

    • Sedimentation ponds of mineral extraction projects;
    • Emergency ponds of wastewater treatment systems (except those combined with biological ponds);
    • Dust and exhaust gas collection systems in cases where no treatment system is required, including emission control systems for boilers, heaters, and generators using gas or DO oil; crematorium exhaust systems; dust collection systems from conveyors, silos, and material storage;
    • On-site wastewater treatment works; septic tanks; grease traps for canteen wastewater; integrated treatment units compliant with legal requirements and environmental technical standards;
    • Cooling water treatment systems using chlorine or disinfectants;
    • Waste treatment facilities of expansion projects without changes compared to previously issued EPs;
    • Facilities of projects operating before January 1, 2022 applying for an EP, except where upgrades or technological changes are made;
    • Facilities under EP issuance, adjustment, or reissuance with no changes compared to previous permits (except where raw materials or processes increase pollutants);
    • Wastewater treatment systems where treated water is fully reused or recycled;
    • Systems where treated wastewater is connected to centralized wastewater treatment systems;
    • Air emission treatment systems with capacity less than 5,000 m³/hour.

    2. Projects NOT subject to EIA but requiring an EP:

    Must conduct trial operation of waste treatment facilities concurrently with:

    • The trial operation of the entire project, or
    • Each investment phase, or
    • Independent waste treatment units,

    after completing:

    • Construction and acceptance of facilities in accordance with construction laws;
    • Installation of automatic and continuous monitoring systems.

    3. Projects subject to EIA and requiring an EP:

    Must conduct trial operation of waste treatment facilities in accordance with the issued EP:

    • Concurrently with the entire project;
    • Or by investment phases;
    • Or by independent waste treatment components.

    4. Notification and reporting obligations:

    • The project owner must notify the permitting authority at least 10 days prior to trial operation;
    • A trial operation report must be submitted at least 20 days before completion
      (45 days for hazardous waste treatment or imported scrap projects).

    5. Duration of trial operation:

    • Determined by the project owner;
    • Must ensure monitoring requirements;
    • Must not exceed 06 months from commencement;
    • Extension (if required) must be notified in writing, stating reasons, and shall not exceed 06 additional months.